Innovative Design at the Homebush Bay Rail Link
Doug
Jenkins Engineering
Manager Reinforced
Earth Pty Ltd |
Ian
Cox Design
Manager Connell
Wagner Pty Ltd |
Greg
Fanning Design
Manager Leighton
Contractors Pty Ltd |
Synopsis: The rail link to the Sydney 2000 Olympic site at Homebush Bay is a landmark project which presented complex technical challenges to both designers and constructors. The project included the design and construction of a number of significant structures including a new station, a driven tunnel, cut and cover arch tunnels, four bridges and retaining walls including reinforced soil walls. Innovative design was required throughout the project to meet the demanding aesthetic and technical requirements of the project within very tight time constraints and project budgets. The design for the on-site civil works was jointly developed by Leighton Contractors, the Head Contractor and Connell Wagner, Leighton’s Lead Design Consultant. In this paper the main features and unique innovations of the project will be described with particular focus on the concrete structures including the cut and cover tunnels where the use of precast concrete arch units, designed and supplied by The Reinforced Earth Company, was adopted as a value engineered alternative.
Keywords: Olympics, Rail, Tunnels, Bridges, Precast
Arches, Reinforced Soil Walls
1. Introduction
The
main objective of the Homebush Bay Rail Link is to provide a rail service to
Homebush Bay for the 1998 Royal Easter Show, for pre and post Olympic events
and for the 2000 Olympic Games. The rail link is an important part of the
infrastructure for the Sydney 2000 Olympics and will provide the primary means
of travel for large crowds attending events at Homebush Bay.
The
$90 million Homebush Bay Rail Link is a landmark project which presented
complex technical challenges to both designers and constructors given the fast
track nature of the project, the necessary integration of a number of civil and
multi-discipline activities, and the need to achieve technical and aesthetic
quality of the highest standard.
The
rail link on-site works, north of the M4 Motorway, comprise a 3km long balloon
loop within the Homebush Bay site which connects the new Olympic Park Railway
Station to the metropolitan rail network between Lidcombe and Flemington
stations through the disused Pippita rail corridor (refer Figure 1).
Figure 1. Site
Location
2.
Project
Description
The
Homebush Bay Rail Link has involved a significant integrated effort by a number
of authorities, consultants and contractors to deliver this key element of the
transport infrastructure for the 2000 Olympics. The key authorities involved
were the Olympic Co-ordination Authority (OCA), Rail Access Corporation (RAC),
and Department of Transport (DoT).
In
July 1996, Leighton Contractors was awarded the design and construct contract
by the Olympic Coordination Authority (OCA) to build the rail link, including
the station. Leighton Contractors engaged Connell Wagner to undertake the
tender design and the detailed design and documentation of all civil works for
the on-site works, as well as the tunnel and station services. Leighton also
engaged Reinforced Earth Pty Ltd to design and supply the cut and cover tunnel
roof arch units and the reinforced soil walls.
In
summary, the rail link on-site works comprise approximately 3km of trackwork
and formation constrained by steep grades up to 3% and tight 180m radius curves
to accommodate existing and future sporting and recreational facilities, a
heritage precinct, buildings, roads and utilities established by the Homebush
Bay Master Plan. This required the construction of significant sections of
tunnel and a number of bridges. The station is located in a section of
bifurcated track allowing a 200m long four-platform station to be constructed
with a capacity of up to 50,000 passengers (or 30 trains) per hour in peak
Olympic mode. It is the largest capacity and most impressive railway station in
Australia. The main elements of the project are:
·
Four bridges: two rail underbridges, one
road underbridge and one pedestrian bridge.
·
560m of cut and cover precast concrete
arch tunnels.
·
300m of driven tunnel.
·
200m long Olympic Park railway station.
·
Cast in situ concrete and reinforced soil
retaining walls.
·
Rock reinforced and shotcrete cutting
wall stabilisation.
·
Tunnel and station mechanical,
electrical, fire and hydraulic services.
·
Trackwork and other railway works.
·
Earthworks and stormwater drainage.
·
1.5km of roadworks.
·
Sewer and water utility adjustments.
Figure 2. General Arrangement of Key Project
Elements
3. Project Requirements
The
Olympic Coordination Authority (OCA) had a number of specific requirements to
be met in the design and construction of the project.
The
stated purpose of the works was to provide rail infrastructure to enable the
operation of a reliable, high capacity heavy rail service to Homebush Bay for
both major events and daily requirements. The rail infrastructure was required
to satisfy a number of important stakeholders including:
·
The long-term owner, the NSW Government,
in terms of design life, maintainability and safety.
·
The rail service operator, in terms of
integration with the metropolitan rail system, operating cost and safety.
·
The OCA and the Department of Urban
Affairs and Planning, by achieving a high standard of urban design consistent
with the OCA’s Public Domain Strategy.
·
The neighbouring property owners (tenants
and users), by minimising disturbance of and intrusion on their activities and
amenities both during construction and operation.
·
The rail users, by providing for a safe
and comfortable rail service.
Programming
was also critical to the OCA. The rail link was to be open to passengers by
31st March 1998, i.e. in time for the first Royal Easter Show at Homebush Bay.
This dictated a very tight design and construct programme (19 months) requiring
a fast track design and documentation phase to keep construction proceeding for
Leighton Contractors. Progressive delivery of design documentation was required
primarily during an initial period of 4-5 months.
Given
the high profile nature of the project and the site, the urban and landscape
design was critical to the OCA. The design intent was to:
·
Provide a memorable rail journey
experience for visitors to Homebush Bay.
·
Provide rail infrastructure works which
are of outstanding design quality and appearance, complementary to the existing
and proposed sports and recreation facilities.
·
Implement the urban design and landscape
works within the OCA budget.
Connell
Wagner worked closely with Leighton’s Urban Designers Hassell Pty Ltd in the
design of a number of structural elements including the bridges, retaining
walls and tunnel portals.
Environmental
performance is a fundamental element in all developments and works undertaken
by the OCA. Ecologically Sustainable Development is identified as underpinning
the environmental philosophy of the Sydney 2000 Olympics and Homebush Bay
Development. Environmentally sensitive design and environmental management were
important requirements of the project. Connell Wagner designed and prepared the
works in accordance with a Design Environmental Management Plan prepared by
Connell Wagner specifically for the project.
Key
technical criteria for the design of the rail link included:
·
Compliance with the design criteria
nominated in the ACER Wargon Chapman Concept Design Report including standards
and requirements of the SRA.
·
Fixed constraints included track
horizontal alignment, kinematic envelope at cuttings and in tunnel, and
vertical clearances at bridge structures.
·
Track vertical alignment was to be
designed to accommodate normal train running speeds of up to 50km/hr.
·
Design life for the tunnels, bridges and
retaining walls was 100 years.
·
The tunnel roof was required to be
watertight.
4. Innovative
Features and Solutions
The
main features and unique innovations on the project are outlined below:
·
The driven tunnel solution under the
Aquatic Centre bus parking area limited the impacts on the amenity and
operation of the popular Aquatic Centre during construction.
·
Precast concrete arches in the cut and
cover tunnels provided a cost effective solution which enhanced speed of
construction and provided flexibility for the variety of spans and varying
finished surface levels along the route.
·
Rock bolting and screeded shotcrete were
used to retain the cuttings in the ramps and tunnels in lieu of concrete pile
and infill panel walls.
·
Avenue A and Avenue B rail underbridges
incorporated girder continuity for the two-span structures and a curved arch
girder profile for enhanced aesthetic appearance.
·
The urban design and aesthetic quality of
the station, bridges, retaining walls, fencing and tunnel portals were
developed to a high standard to minimise the visual impact of the rail
infrastructure and to complement the existing and proposed high quality sports
and recreation facilities.
·
Station design utilised extensive use of
precast concrete structural elements to minimise the construction programme.
These
and many other innovations were an outcome of the effective teamwork between
contractor and designer and were carried out within the framework of
Ecologically Sustainable Development (ESD) principles and the need to achieve a
high standard of urban design. The extensive use of precast concrete elements
in both the civil works and building works at the Homebush Bay Rail Link was
highly successful in terms of quality and programme.
The
main features and unique innovations of the project are described in further
detail below.
Driven
Tunnel
The
driven tunnel was an innovative alternative, proposed at the time of tender and
acknowledged by the OCA as being a major factor in Leighton’s successful
tender. The driven tunnel limited the impacts on the amenity of the popular
Aquatic Centre during construction and facilitated early construction of the
Olympic Boulevard. The “horse-shoe shaped” tunnel was driven through weathered
shale geology and relatively shallow cover up to a maximum of 12m. The northern
end of the tunnel was particularly complicated, given the relatively large 9m width
of the tunnel resulting from track bifurcation and 4-5m of relatively poor
quality class IV and class V shale above the crown. Careful attention was paid
to a major existing utilities services corridor above the tunnel in this
location. Spiling bars were installed above the crown to assist in the support
of the ground ahead of the face to reduce settlement, and to also allow grout
filling of open joints in the rock mass. Tunnel support comprised a primary
lining of shotcrete and temporary Swellex rockbolts followed by a permanent
secondary steel fibre reinforced shotcrete arch lining of a minimum 150mm
thickness. A waterproof membrane was installed in the crown of the tunnel to
prevent any “drips or discernible flows” (as required by the contract), from
entering the tunnel.
Cut
and Cover Tunnels
The
design and construction of the cut and cover tunnels was complicated by the
variable cross section, variable cover, the proposal to build a hotel over part
of the route, the substantial excavation required, and the provision for
existing roads across the route. In the area of the Homebush Bay Hotel, the
concrete pile and infill panel wall was retained to transfer the future
building loads to competent rock, while the remainder of the cut and cover
tunnel was constructed using precast arches manufactured by the Reinforced
Earth Company. Precast arches were selected because of:
·
Speed of construction and cost.
·
Flexibility in handling a variety of
spans and founding level.
·
Load carrying capacity, given the variable
cover.
·
Ability to protect efficiently the tunnel
from water ingress.
The
design and installation of the cut and cover tunnel arches are described in
further detail in Section 6 of this paper.
Cutting
Wall Stabilisation
An
assessment of the geotechnical investigation work undertaken by OCA prior to
calling tenders indicated that Class I to Class III shales existed over most
areas to be excavated. In tendering for the project, extensive use of rock
nailing was made to support the cuttings in lieu of previously proposed, more
expensive, solutions such as pile and infill panel walls. The foundation
conditions were also suited to the use of high level sill beams for the cut and
cover structure in lieu of piled foundations. This approach not only saved considerable
cost on the project but also enabled ambitious time targets for the project to
be achieved. The rock nailing proposal involved the use of permanent “CT”
rockbolts with steel fibre reinforced shotcrete to maintain the integrity of
the rock face. It had been proposed that precast concrete panels be used to
face the piled walls. While this method proved to be appropriate in the station
box, it was replaced with a combination of screeded shotcrete and cast in situ
concrete L-walls in the cuttings. Again, this technique provided considerable
savings in time and cost to the project.
The
use of shotcrete and permanent rockbolts for the cutting wall stabilisation
proved to be cost effective and provided the benefit of quickly developing
several work fronts, thereby providing greater flexibility for this
construction operation.
Bridges
The
bridges over Avenue A (Australia Avenue) and Avenue B, along with the retained
embankment on the approaches, presented a significant visual element of the
Homebush Bay area. Connell Wagner, together with Leighton’s urban design
consultant, Hassell Pty Ltd, developed a girder design for the bridges which
reflects the significance of their position.
Both
rail underbridges consist of two spans of concrete through girders with a
ballast top deck which is continuous over the centre blade pier. Alternative
steel superstructures were considered for the bridges, however concrete was
preferred by the OCA in terms of appearance and long term maintenance.
Avenue
A bridge carries a single track with equal spans of 22m and an onerous 36°
skew. Avenue B bridge carries twin tracks with equal spans of 18m and a normal
skew of 6°. The girders for both bridges are post tensioned longitudinally in
three stages and the deck is post-tensioned in both directions. The girders for
Avenue A were constructed as precast elements (manufactured in Queensland)
while the shorter spanned Avenue B bridge was cast in situ. The urban design of
the bridges was very important to the OCA given the significance of their
position on the site, and the structural design of the bridges was to a great
extent architecturally driven. The interesting and innovative features of the
design of both bridges were the:
·
Curved arch facing profile of the
external face of all girders designed to make the girders appear lighter,
thereby reducing the apparent depth and enhancing the overall appearance.
·
Continuity of the girders over the centre
support to eliminate the conventional headstock at the centre pier and avoid
the need for a significant and highly visible centre joint.
·
2.1m depth adopted on all bridges for
consistency.
These
features are indicated in Figure 3.
Figure 3. Avenue A Bridge
Urban
Design
Leighton
engaged Hassell Pty Ltd to undertake the urban design for the project to
achieve OCA’s objectives. In the design development, Hassell’s approach was to:
·
Recognise the rail corridor’s monumental
scale.
·
Express structures with simplicity and
clarity of architectural expression.
·
Use a family of elements unified by consistent
materials and colours.
This
had a particularly significant effect on areas such as:
·
Retaining walls and joint locations -
form, finish, panel sizes and joint locations in all wall forms to be
compatible (dark grey colour was adopted for all major walls).
·
Use of reinforced earth walls with
similar panel sizes to the major walls and at all portals.
·
Bridges - use of curved profiles on major
girders and detailing of the reinforced earth wall abutments.
Olympic
Park Station
The
award winning Olympic Park railway station is a very innovative, world-class
facility. It is the central element of the Rail Link project. The innovations
embodied in the project are the outcome of significant work from many
contributors, including the OCA, Leighton, Hassell, Tierney and Partners and
Connell Wagner.
The
significant concrete elements adopted for the railway station were:
·
Use of precast concrete wall panels for
the station box, manufactured to a high level of finish quality.
·
Precast concrete columns from platform
level to support the large span steel roof structure .
·
Post tensioned mezzanine level suspended
concrete slab to provide the primary means of egress from the platforms.
5. Environmental
Achievements
The
OCA required the contractor to:
·
Recognise environmental performance as a
fundamental element of the project in line with the NSW Government’s
environmental commitments for the Olympics.
·
Incorporate the principles of
Ecologically Sustainable Development (ESD).
·
Comply with the Homebush Bay
Environmental Strategy.
Connell
Wagner developed all aspects of the design in accordance with the Design
Environmental Management Plan which it developed for this project. Leighton
Contractors carried out a critical review of the Plan with an emphasis on cost,
programme and buildability aspects.
Connell
Wagner’s environmental assessment process for the Homebush Bay Rail Link
included an evaluation of potential environmental impacts associated with a
product from its virgin material extraction through the stages of refining,
manufacture, distribution, use, maintenance and waste disposal. The assessment
process was project specific and used ESD analysis to ensure that the design
not only addressed the relative impacts of alternative materials, but also
included features which minimised the environmental impacts associated with
material selection and construction. Connell Wagner’s assessment process
offered a systematic approach to decision making based upon understanding of
the environmental attributes associated with a product. Key criteria evaluated
included life cycle cost, resource depletion, embodied energy, inherent
pollution, suitability and availability.
The
significant benefits derived from this process were:
·
Confirmation that many proposed products
achieved the required outcomes.
·
The recycling of excavated shale within
the site for use as backfill behind retaining walls and over cut and cover
tunnels.
·
The use of materials which are
manufactured using recycled or natural raw materials, eg recycled concrete for
sub-base and HDPE in subsoil drains and strip drains
·
Incorporation of waste by-products such
as flyash to reduce cement content in concrete.
·
Adoption of local technology and
manufacture to promote Australian products and to reduce energy in transport.
·
Separate track and non-track drainage
systems to reduce demand on pumps and rising mains.
·
Maximum use of gravity drainage to reduce
energy demand and life cycle cost.
·
The use of oil / grease separators and
silt fencing to control sedimentation and contamination of receiving waters.
Leighton Contractors extensive experience in environmental management enabled this project to be carried out in an environmentally responsible manner. The establishment and maintenance of environmental protection devices was afforded a high priority in order to satisfy the OCA’s environmental objectives.
Environmental
monitoring and reporting provided OCA with a high level of confidence in
Leighton’s ability to carry out the works without compromising their
environmental responsibilities.
6. Design and
Supply Works by The Reinforced Earth Company
The Reinforced Earth
Company was initially involved with the Homebush Bay Rail Link Project through
the design and supply of Reinforced Earth® retaining walls and bridge
abutments. In all, six bridge abutments and 6,500m2 of retaining
walls were supplied by Reinforced Earth for the on-site works.
The successful tender
design prepared by Leighton Contractors and Connell Wagner for the cut and
cover sections of the tunnels proposed construction of bored reinforced
concrete piled walls with a precast prestressed concrete plank roof. This was
consistent with the design brief issued with the tender documents which
suggested that a precast concrete arch was an unsuitable solution for the
tunnels because:
·
There would not be enough cover over the crown
of the arch.
·
The volume of excavation would be significantly
greater than for a rectangular section.
The Reinforced Earth
Company proposed the use of TechSpan® arches for all the cut and cover tunnels
during tender negotiations for the retaining wall contracts. In addition to the
issues raised in the tender design report the following concerns needed to be
addressed before an arch solution could be accepted:
·
Stability of the arches under train impact
loading in the twin tunnel sections.
·
The ability of precast arches to deal with the
complex geometry.
·
Waterproofing of the precast joints to comply
with the specification requirements.
These issues were
successfully resolved and final design work on the arch structures started in
November 1996.
Retaining Walls and
Bridge Abutments
The first contract
awarded was for the design, manufacture and supply of Reinforced Earth
retaining walls for the bridge abutments and ramp walls of the Homebush Bay
Rail Link on-site works. This contract was later extended to include the tunnel
arch collar walls at the portals.
The Reinforced Earth
walls for these areas of the project are unique in that a 3m long by 1.5m high
rectangular panel was used and the joints are in a stretcher bond arrangement.
The panels all have a black oxide added to the concrete with the ramp walls
having a false vertical joint down the centre of the panels and the abutment
panels having a number of horizontal grooves (refer Figures 4 and 5).
At a later stage, The
Reinforced Earth Company was awarded a contract for the design, manufacture and
supply of three Reinforced Earth structures for the connection between the
Homebush Bay Rail Link and the existing main western rail line at Flemington,
known as the Pippita Corridor.
The two rail bridges
were constructed using the Terraset® precast concrete panel system. Terraset is
a rectangular panel, 2.1 metres high by 1.7 metres wide. Both structures had
the same finish as used on the walls of the new Homebush Bay Drive Overpass,
also designed by Connell Wagner. Both structures had a maximum height of 6.0
metres and were designed to support full rail loadings and the stresses induced
by the overhead wire structures. The third bridge, road over rail, was constructed
using the traditional cruciform precast concrete panels.
Figure 4. 3m x 1.5m rectangular precast concrete panels,
constructed in a stretcher bond configuration
Figure 5. TerraSet abutment walls
TechSpan Arches.
Following award of the
contract for design and supply of the TechSpan arches the arch profiles were
optimised to suit the shale founding levels and track clearance envelopes. A
single track enters the tunnel, splits into 2 at the station and returns to a
single track before exiting the tunnel.
In total 9 arch
profiles were adopted varying in span from 8m up to 19m. An insitu reinforced
concrete infill was required at the interface of the different arch sections.
In all, there were
three areas of cut and cover tunnel adopted on the project. Cut and cover
tunnel 1 is located before the driven tunnel and cut and cover tunnels 2 and 3
are either side of the station. The design and construction of the cut and
cover tunnels were complicated by the changing cross sectional geometry due to
track bifurcation either side of the station. The arches were typically
supported on cast insitu concrete footings founded on rock. Where the arches
were founded at a high level such as in cut and cover tunnel 1, the walls of
the tunnel were stabilised with rock bolts and shotcrete.
The key advantages of
the TechSpan arch solution were:
·
Reduced supply cost.
·
Rapid erection.
·
Project specific arch profiles provided the
required track clearances with no additional earthworks.
·
Minimal on site concrete works.
·
No obstruction to the track alignment during
construction.
Figure
6. Installation of the 19 x 8 arches. Twin 10 x 3 arches can be seen behind.
Figure 7. Finite Element Analysis of the twin arches under impact
load
Figure 8. Typical cross sections compared to the profile of
the contiguous pile and plank solution
The TechSpan design
process has two unique features, which enhance the efficiency of the arch
design:
·
The arch profiles are designed on a project
specific basis, taking account of the actual clearance requirements and
vertical and horizontal loads, to provide an optimised arch shape with minimum
bending moments in the finished structure.
·
The arch analysis is carried out using a
non-linear finite element analysis program, which models the loading sequence
on the arch during erection and backfill.
To accommodate the
diverging track clearance envelope the arch spans were increased in
approximately two metre steps up to a maximum of 19 metres. Twin arches were
adopted when the single spans became too large approximately 90m from either
side of the station. The 19 metre span arch connected with a twin arch of two
ten metre spans, with a central headstock and column support. The central
support, which was designed by Connell Wagner, was required to carry a train
impact load of 1000 kN. In order to verify that the arches would provide
adequate restraint to the top of the column, without excessive deflection,
Reinforced Earth carried out a finite element analysis of the full system,
which showed minimal deflection under the design impact load (Figure 7)
Figure 9. Typical section through the twin
arches
TechSpan Construction
Construction of the
TechSpan arches started early in 1997 and was completed by June 1997. The
system is designed to allow erection of arch units to proceed using only one
crane after the first four units have been erected. For the rail link project
Leighton chose to use two cranes for the whole project to provide additional
flexibility and faster erection rates, allowing them to place up to 40 arch
units a day (about 30 metres length of arch). For program reasons construction
to the east of the station started at two separate locations, and proceeded on
four fronts, requiring careful monitoring of joint thicknesses to ensure that
the final closing precast elements could be placed without difficulty.
Figure 10. Three arch profiles, twin 10 x 3, 19 x 8 and 17 x
8. The arch in the foreground is 15 x 7
Figure 11. The completed twin tunnel
TerraTrel ® Faced Reinforced Earth.
For a 50 metre section
of the twin arches where the shale foundation level dropped down vertically by
3 metres, two TerraTrel faced Reinforced Earth walls were constructed to form
the arch foundation in lieu of modifying the arch profile. The TerraTrel walls
are designed to support the full loads applied by the arch structure. To
provide a full 100 year service life, the facing was sprayed with 100mm thick
shotcrete.
TerraTrel was also
used for two other applications on this project. It was used to form the
TechSpan arch collar walls at the station and to form basement walls for the
hotel development that crosses one section of the tunnel.
|
Figure 12. Typical section through the TerraTrel arch
foundation
Innovations at the
Homebush Rail Project, And Their Development
The Homebush Bay Rail
Link saw a number of innovations from The Reinforced Earth Company:
·
Use of the TechSpan system for rail tunnels.
·
Stepped arch profiles, and twin arches supported
on a central column.
·
Single piece arches for small span and height.
·
Large span arches with shallow cover.
·
TechSpan arches supported on Terratrel walls.
·
First large scale use of Terraset facing in
Australia.
·
Use of large rectangular panels in vertical
walls.
Since the introduction
of the TechSpan system in Australia in 1990 it has gained increasing acceptance
for use in large projects requiring a significant design input from the arch
supplier. The system will find increasing use both in road and rail tunnels,
and with extended range of spans at both the lower and upper end of the scale.
Whilst the Reinforced Earth systems are widely known and accepted in the construction industry, it is becoming increasingly necessary to provide project specific surface finishes and panel shapes. The Reinforced Earth Company will continue working with its clients and their consultants to provide new products that satisfy the aesthetic needs of the project whilst maintaining the traditional virtues of economy, speed of erection, and durability.
7. Conclusions
In summary the completed project presented complex technical challenges to both designers and constructors which required the implementation of a number of innovative solutions to enable aesthetic and technical requirements to be achieved within very tight time constraints and project budgets.
The project included significant concrete structures including tunnels, bridges and retaining walls all of which have been designed and constructed to achieve the OCA’s requirements, presenting a high standard of urban design whilst achieving the technical and functional requirements of a reliable, high capacity heavy rail service to Homebush Bay.
The
completed project passed its first major test with the hugely successful
transport operation during the 1998 Royal Easter Show, during which more than
1.8 million passengers passed through the new station.
The authors wish to acknowledge the support of the Olympic Coordination Authority for this submission to the CIA Concrete 99 Conference.